What should a contractor do if there are changes required after project completion certification?

Ignore them, if certified

Address them before final payment

Addressing changes required after project completion certification before final payment is crucial for several reasons. First, it ensures that the work meets all contractual agreements and specifications, which is essential for maintaining the integrity of the project and satisfying the client's expectations. By resolving any outstanding issues before the final payment is made, the contractor reinforces their commitment to quality and builds trust with the client.

Additionally, addressing changes at this stage allows for the correction of any potential defects or oversights, thereby reducing the likelihood of disputes or liability claims in the future. This proactive approach also safeguards the contractor's reputation and can foster positive relationships, leading to future opportunities and referrals.

Furthermore, leaving changes unaddressed could lead to problems during inspections or even legal ramifications if the project does not comply with local codes or client specifications. Overall, prioritizing this step is an essential aspect of responsible project management and professional integrity.

Get further explanation with Examzify DeepDiveBeta

Document them for the next contractor

Report to the licensing board